Top Menu

Jump to content
    Global modules

    Global modules

    • Home
    • Projects
    • Activity
    • Work packages
    • Gantt charts
    • Calendars
    • Team planners
    • Boards
    • News
    Home
    Home
Help
    Getting started
    • Introduction video
  • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support
  • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation

User menu

Sign in
Forgot your password?

or sign in with your existing account

OpenProject ID Google

Side Menu

Collapse project menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

Expand project menu
General discussion
  1. OpenProject Community
  2. OpenProject
  3. Forums
  4. General discussion
  5. Constraints in work package hierarchy and versions

Constraints in work package hierarchy and versions

Added by Bernd Petraus over 9 years ago

Hi there,

I’m just testing the scrum functionality at the moment. And I like it very much. While playing around two questions came in my mind:

Is there a way to create constraints re. the work package hierarchy, depending on the work package typ? For example, a type “subtask” can only be splitted in other “subtasks” or “tasks” and a task can only be splitted in “process”, like it is done in classical project management approaches.

Furthermore, is there a way to create aconstraint re. the version? For example, that just work packages of type “task” can have a version.

That seems quite straight, but that would be necessary to fit in our acutal project management methodology.

Best regards

Bernd


Replies (2)

RE: Constraints in work package hierarchy and versions - Added by Robin Wagner over 9 years ago

Hi Bernd,

it’s not directly possible to configure which work package can be set as a parent or a child but you can use a workaround to at least configure which types can or cannot have child work packages.
To do this you can configure a type to be a “milestone”. (“Administration” > “Work package types” > “Select type” > Check box “Is milestone”).
Types which are defined as milestones cannot have any sub work packages (you’ll receive an error message when trying to set a milestone as a work package parent).

Constraints regarding versions are currently not possible. You can only define whether or not work packages can be added to a version: When a version is set to “locked” or “closed” it is not possible to assign a work package to it.

Best regards,
Robin

RE: Constraints in work package hierarchy and versions - Added by Bernd Petraus over 9 years ago

Hi Robin,

thank you for the hint. (using milestones as lowest hierarchy element) Unfortunately milestones are limited to one day, so there’s no way to define durations. But, good to know.

So, others may find this feature useful as well. I will create a feature on the wish list on tomorrow.

Best regards

Bernd