Can show the actual progress of the work package on the Timeline
Added by weiyu gu almost 9 years ago
Currently in the software input program, display program (“time line”) can be realized, also have local inputs the actual elapsed time, but in the time line chart couldn’t see the actual progress of the project activities, no report shows that the project actual progress and plans are compared. Whether this function can be achieved?
Replies (1)
Hello Weiyu gu,
thanks for your question.
The timeline in OpenProject does indeed not reflect the spent time.
Instead, the progress is shown by the work package status which can be added as a column to the timeline report.
Best,
Robin