Top Menu

Jump to content
    Global modules

    Global modules

    • Home
    • Projects
    • Activity
    • Work packages
    • Gantt charts
    • Calendars
    • Team planners
    • Boards
    • News
    Home
    Home
Help
    Getting started
    • Introduction video
  • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support
  • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation

User menu

Sign in
Forgot your password?

or sign in with your existing account

OpenProject ID Google

Side Menu

Collapse project menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

Expand project menu
General discussion
  1. OpenProject Community
  2. OpenProject
  3. Forums
  4. General discussion
  5. Timelines - Not following earlier finishing dates?

Timelines - Not following earlier finishing dates?

Added by Deleted user over 11 years ago

Hi, I refer to this video: https://www.openproject.org/projects/openproject/wiki/Timelines
1st: I have no submenue @ timelines in version 3.0. So i have no menue-Items called “dependencies” and no “planning elements”.
But I think i can set theses things at other places. All ok with my installation?

2nd:
I don´t get dependencies managed. If I have an item that is “the follower of” another item, with 2 days offset. The dates of the follower changes, if i enter a date in the preceeding element that is later then the initially planned finishing date. OK, fine!
But if i enter in the first item an earlier finishing date, the following item does not follow the new finishing date + 2 days of the preceeding elemet, it just stays on the old planning dates.

What am i missing, what do i have to do? (In example it is one relationship, but i want that 30 tasks update if i change the first element, so i cant delete all planning-dates in the followers)

3rd: What is the meaning of “In Beziehung zu” “in relation to” another task?? What means relation in practice? What happens if i set this? I understand blocked, following; (these are relations) but what happens if i say it has “a relation to” another item???

Apologize my bad english pls.
Thanks
Greetings Thomas

P.S.: Example to 2nd question:
1st item:
scheduled: 10.02.2014-15.02.2014
2nd item:
not scheduled, defined as following item1 + 2 days

View in timeline:
1st item: 10.02.2014-15.02.2014
2nd item: 17.02.2014-17.02.2014

editing 2nd item, because i cant work the 37 hours planned for 2. item in one day ( no resource planning and working hours available, right?)
editing: 17.02.2014-22.02.2014

A few days after initial planning:

1st item finishes earlier:
changing finishing date 1st item to: 13.02.2014

problem: 2nd item stays at 17.02.2014-22.02.2014. This item should have moved 2 days to 15.02.2014-20.02.2014


Loading...