Gantt Chart currently not useable?
Added by Tobias Schmitt over 8 years ago
Hi,
am I right that there is currently no possibility to define “work days” in OpenProject?
If so, the whole Gantt chart makes currently no sense if you are using relationships between work packages.
(Saturday and Sunday are currently used as working days, which is simply not the case in most countries)
At the moment the gantt shows wrong “end dates” for all my tasks with relationships because of this.
Thanks,
Tobias
Replies (1)
Hi Tobias,
you are right, this feature would be very helpful. You are working in the software industry, right? Please feel free to contribute to the project and send us a pull request on Github
Bests
Niels