Top Menu

Jump to content
Home
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

General discussion
  1. OpenProject
  2. Forums
  3. General discussion
  4. Changing dates combined with dependent workpages

Changing dates combined with dependent workpages

Added by QI Employee almost 10 years ago

Currently we’re testing Openprojects in our organisation. We have recurring tasks, which consists of several components. I created a template project with serveral workpackages underneath, for example:

Installation hardware Project X

ship hardware to customer
Plan service engineer
Connect hardware on-site
Power-on system and runs checks

etc

These workplaces are dependent on each other (follow up x days)

When I want to change the starting date of this project anc move it ahead in time, I modify the date of the first workpackage and all other packages are correctly modified as well. For example the project is delayed 7 days.

But when I need to move a project back in time, and I change the date 7 days back in time, then the underlying packages do not move along and are not modified. The result is that there enddates don’t match anymore.

Is there a reason for this? Am I doing something wrong?
Would you suggest another approach to move a bunch of work packages ahead or back in time, simultaneously?


Replies (1)

RE: Changing dates combined with dependent workpages - Added by Robin Wagner almost 10 years ago

Hello,

thanks for you question.
Actually, this behavior is currently by design:
When a deliverable (such as a phase or a milestone) is delayed, the work packages following this deliverable need to be pushed in the future as well.
However, the reverse is not necessarily true since finishing a deliverable earlier may not necessarily mean that the work packages following this deliverable should be completed earlier as well.
Arguably, this can however be solved by using a buffer time.

There is actually a feature request for the behavior you describe:

Feel free to check whether this feature request matches your requirements.

Best regards,
Robin