[Solved] Summary of working hours spent per user?
Added by karel lang over 9 years ago
Hi guys,
this is probably very trivial question, but i cant find answer in forums or google ..
I need to display summary of working hours (time spent) that employee spent working on per specified time frame (month).
Employee works on different projects with diff. work packages, is there some easy way to summarize hours per month per employee?
Thank you
Replies (2)
Hi Karel,
Yes, there is, via the cost reports, you can specify the time frame and/or project(s).
Please check out this User Guide for more information:
https://www.openproject.org/help/user-guides/time-costs/time-costs-reports-cost-report-plugin/
Best,
Maya
Yeah!
that’s it, you’re now my hero :-)
Thanks a lot for your dedicated, fast and kind answer!
with best regards,
in debt,
Karel