Newbie Questions about work packages and general usage
Added by Mario Ganz over 9 years ago
Yay, I managed to install Openproject 4.0 and it is running nicely.
I want to coordinate an already running project based in higher education on education. Thus, a completely non technical project. :-D
I hava a structure which is divided into workpackages 1 - 8 which contain general descriptions of the specific project part. These work packages then contain 27 deliverables in total.
These deliverables have deadlines and a period which they are running, e.g. Deliverable 1, Report running from 01.10.2013 to 31.03.2015.
Therefore I need a structure like this
Project | Workpackage 1 -> description |---- Deliverable 1 -> task |---- Deliverable 2 -> product |---- Deliverable n -> event | Workpackage 2 -> description |---- Deliverable 1 -> report |---- Deliverable n -> whatever | Workpackage 8 -> description |---- Deliverable 27 -> ...
Deliverables in OP confuse me, because they always demand a task. I would like to reflect the existing structure in order to make it easy for the project partners to use OP.
How would you do this. Seeking advice and ideas.
Thanks
Replies (3)
Hi Mario,
congrats on installing OpenProject :)
Could you provide some details which changes you want to make to the project structure?
Depending on the size of your project and it’s sub-elements, it may make sense to create separate sub-projects for them (you can still display the work packages in the work package list of the parent project).
If you feel that deliverables do not properly fit your need, you can alternatively use other work package types or create your own types (Administration > Types).
Best,
Robin
Well, I used a workaround now.
I disabled the “none” workpackage as it seems that I just cannot add work packages that act as headings.
Basicly I just entered all Deliverables with their deadlines in as “Deliverable” and assigned a person.
Also, I created categories, that reflect the name of the work packages.
Therefore my structure now looks like this:
To structure your project in OpenProject:
Create Work Packages: Divide your project into Work Packages 1-8, each containing general descriptions of specific project parts.
Define Deliverables: Within each Work Package, define the 27 deliverables with their respective deadlines and periods.
Use Gantt Charts: Utilize Gantt charts in OpenProject to visualize the timeline and dependencies of your deliverables.
Assign Responsibilities: Assign team members responsible for each deliverable to ensure accountability.
Track Progress: Regularly update the status of deliverables to track progress and ensure timely completion.
By following this structure, you can effectively coordinate your project in OpenProject, even if it's non-technical in nature.