Added by Michael Freitter over 9 years ago
Greeting,
in other project management tool, ther is possible to relate the work packeges not only serial, but parallel, …
e.g. Start-to-Start link, Finish-to-Finish link, Start-to-Finish link.
It is also in OpenProject possible?
Regards
Michael
Replies (1)
Hello Michael,
you can use work package relations to create those relationships between work packages.
By selecting “follows” or “precedes” you can create those relationships with an optional delay in the work package show form:
Best,
Robin