[bug] "% done" of user story always at 0%
Added by andrea olivotto over 9 years ago
I have a user story with some tasks, created using the backlog plugin.
The “% done” of user story is correctly calculated only if the “Remaining Hours” and “Estimated Time” of subtasks are empty.
If both are set to “0.0”, “% done” of user story is 0%.
Playing with the sprint task board, sometimes the “Remaining Hours” and “Estimated Time” fields are suddenly set to “0.0” (example: move the task to Closed column, the back to “In progress” column). Then, I need to manually empty these fields to have the “% done” of the parent user story correctly calculated.
Is this a bug or… a feature?
Andrea
[update: its a bug :-)]
Replies (3)
Hello Andrea,
thanks for reporting this issue.
This seems indeed to be a bug (#18126).
The remaining hours should be set back to the prior state when moving from a closed column to an open one in the task board.
Best,
Robin
Thanks Robin for your support, very important for me.
And for my R&D office :-)
Andrea
Robin,
I’m reading the #18126 bug.
If I’m not wrong the wrong behavior occurs even when we just close a task: the user story “% done” goes to 0%.