Added by Qiong Wu about 10 years ago
Hi everyone, the problem is as stated in the topic, unfortunately I cannot see tasks of subprojects associated with my project on the timeline site of my project.
Even if I choose to include subprojects in the edit timeline report project timeline window, these tasks do not appear on the timeline, can someone offer help?
Thanks & Best Regards
Replies (2)
Have you enabled status reporting in subproject?
https://www.openproject.org/help/user-guides/project-settings/manage-status-reporting/
Regards,
Igor
ah okay i didnt do that, thanks!