Added by Alexandru Matei almost 10 years ago
Good morning,
Is there a possibility to show the spent time (logged time) as a column in the work package list ?
Currently only the estimated time can be displayed as a column.
Please see attached image for more details.
Thanks!
Replies (1)
Hello Alexandru,
thanks for your question.
Currently it is unfortunately not possible to display “Spent time” as a column in the work package list.
You can however display “Labor costs” (if your objective is to determine the cost and their sum associated with work packages).
Feel free however to open a feature request in the Wish List.