Work package filter do not consider the "Spent time" field
Added by Andreas Metz about 10 years ago
Hi @ all,
short question to the “Work package” menu entry. In case i want to apply a filter for the work packages it is currently not possible to consider the spent time field.
Filter for the Estimated time and remaining time is always available. It is also not possible to list the spent time as a column.
Could anyone explain, why it is not possible to show the spent time in the filter screen? From our point of view, it would be great feature.
We are using OpenProject 3.0.8 at the moment.
Thanks in advance for any help.
Replies (1)
Hi Andreas,
sorry for the late reply.
You are right, “Spent time” can currently not be selected as a work package filter.
Feel free however to open a feature request in the Wish List.
Thanks,
Robin