Added by Artem S'omushkin 9 days ago
Hi There
We are just evaluating OpenOffice as replacement for MS Project and I came to the problem that I can't create a report of planned work per resource.
E.g I have created a project and work packages. I have assigned members to it and added work estimates.
Then I've used a Gant chart to plan the tasks in time, including duration.
Now based on start date, task duration and assignee, I would like to estimate resource utilization per calender week or month. E.g. to see if resource is underutilized or overutilized. Unfortunately I can't see this feature for planned work, only for actual work.
Is it possible somehow without export into Excel and writing all formulas there?
Thanks for feedback