Added by Nicholas Konidaris 2 days ago
Good day, all
I have searched in documentation and forms for a while and apologizes if I missed this information elsewhere. I have found when looking at the Gantt chart view close to the end of a year, the work packages that start in the new year are pushed to a separate page (e.g. Page 2 of 2). I am not sure if this is a bug or intentional but being able to see all packages over a new year period would be extremely helpful.
I have tried zooming out to multi-Month and multi-Year views, checked filters, and visibility settings with no luck. Any help would be greatly appreciated!
Kind regards
Nicholas
Replies (1)
Hello Nicholas,
the Gantt chart itself should not have an effect on the page count. Looking at your screenshot, I assume that you sorted the work packages in your list by date. That way, the last starting/ending work packages appear at the bottom of the list. Since you selected to display only 20 work packages at once, OpenProject created a second page for the last remaining work packages. If you change the number of dispayed work packages per page, the Gantt chart will show them all at once. Example:
Best,
Alexander