Top Menu

Jump to content
Home
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      OpenProject ID Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

Plugins
  1. OpenProject
  2. Forums
  3. Plugins
  4. Budgets. Actual unit costs don't summarize

Budgets. Actual unit costs don't summarize

Added by Oleh Puzanov 10 months ago

Good afternoon,

It appears, that the Actual unit costs don't summarize and show only the latest unit cost log.

I am sure it worked well in v13, perhaps the new option in settings has been added? 


Replies (2)

RE: Budgets. Actual unit costs don't summarize - Added by Alexander Stock 10 months ago

Hello Oleg,

thank you for mentioning this. You did everything right. I am afraid this is in fact a bug and not related to your settings.
Currently, when you open a budget, in the actual unit costs, the last entry just replaces a preceding entry, if both have been booked on the same work package.
So in your example, if you would have booked a unit onto a different work package in this project, using the same budget, that would appear in the list.

Please find here a bug report where this is explained in more detail:
https://community.openproject.org/wp/55895

The costs are not lost though. The value on the right side still sums up correctly (as you highlighted red).
I encourage you to watch the corresponding bug report in order to receive a notification once this is fixed.

Best,

Alexander

RE: Budgets. Actual unit costs don't summarize - Added by Oleh Puzanov 10 months ago

Hi Alexander, 

Thanks for your detailed clarification and the bug report. I will follow this thread.