Top Menu

Jump to content
Home
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

General discussion
  1. OpenProject
  2. Forums
  3. General discussion
  4. Losing days when planning

Losing days when planning

Added by Maurice Kunze 10 months ago

Hello,

we have the following problem:
When we plan a project with some milestones we are losing some days in our planning.
Lets take this simple example:

The Task "Vierte Aufgabe" has a "follows" relationship with the milestone "Erster Meilenstein".
Now the problem is that the task which has this relationship with the milestone always starts one day after the certain milestone.
When planning projects like this for months or years in advance we will lose a good amount of days and the project will get pushed forward just because we used the relationships for the workpackages.
Is there some workaround for this scenario or has someone else also encountered this?


Replies (1)

RE: Losing days when planning - Added by Alexander Stock 10 months ago

Hello Maurice,

work packages indeed automatically start 1 day after a milestone. I understand that this can lead to the loss of scheduling time especially in e.g. multi-year projects. Currently, there is no workaround to prevent this, I am afraid. However, there is a feature request in place that aims to change this:

https://community.openproject.org/wp/45981

I added a vote on your behalf.

Best,
Alexander