Content
You are here:
Question about Available Hours Per Day and Work Package "Cost" planning
Added by caleb caleb 5 months ago
Hello,
I'm wondering if there's some way to combine Team Planners / Calendars view with planning by Work Package costs.
E.g. I can indicate that there's 8 hours available per day, and then stick a two 2 hour and one 4 hour work package in there, and indicate the day is now "full" to help me avoid putting further work packages on that day. Or just some approximation of this. Is this possible? We're using version 13.4.1 since that's the latest version available on Elestio.