Top Menu

Jump to content
Home
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

General discussion
  1. OpenProject
  2. Forums
  3. General discussion
  4. % Complete with custom percentage rather than dropdown

% Complete with custom percentage rather than dropdown

Added by Ivan Minárik 11 months ago

Hello all, 

I need to assign % Complete to numerous states of a custom wp. Is there a way to assign a custom value (say 26%) to a status rather than those available in the dropdown? Or can a dropdown be adjusted for values? What is the reason to put a numeric value into a dropdown in the first place?

Thank you for any help.


Replies (3)

RE: % Complete with custom percentage rather than dropdown - Added by Alexander Stock 11 months ago

Hi Ivan,

I assume this is a custom field named "% complete" which is basically a list with pre-configured entries. If you want a custom field to be e.g. an integer instead of a list, you can create a new field via the administration panel which better suits your needs. Please find here a guide on working with custom fields:
https://www.openproject.org/docs/system-admin-guide/custom-fields/#manage-custom-fields

Best,

Alexander

RE: % Complete with custom percentage rather than dropdown - Added by Ivan Minárik 11 months ago

Hi Alex, 

thank you for your suggestion. I was considering creating a custom field, but there is then no way to automatically adjust the value based on task status. % Complete is not a custom field but a default one, where either work-based or status-based progress is recorded (and it doesn't work too well...). 

For reference, this is the feature: https://www.openproject.org/docs/system-admin-guide/manage-work-packages/work-package-status/#create-a-new-work-package-status and the attached image in my first post.

I don't think the dropdown is legally editable (i.e. in a config or through UI).

Cheers,

Ivan

Alexander Stock wrote:

Hi Ivan,

I assume this is a custom field named "% complete" which is basically a list with pre-configured entries. If you want a custom field to be e.g. an integer instead of a list, you can create a new field via the administration panel which better suits your needs. Please find here a guide on working with custom fields:
https://www.openproject.org/docs/system-admin-guide/custom-fields/#manage-custom-fields

Best,

Alexander

RE: % Complete with custom percentage rather than dropdown - Added by Alexander Stock 11 months ago

Hi Ivan,

understood. I though your were referring to a custom field you already added which is something others have been working with recently.
I am afraid that these default values cannot be changed currently. If you want to bind a status to a % complete value, these drop-down options are the only ones to chose from at this point.

There is a similar feature request where you maybe want to add your vote/comment: https://community.openproject.org/wp/48715

If you want to calculate the % complete value automatically based on the values at work and remaining work, then you need switch to a work-based progress calculation: [1]
 

Please note that this eventually overwrites your current values.

That way, also other values are possible for % complete.

Best,

Alexander

[1] https://www.openproject.org/docs/user-guide/time-and-costs/progress-tracking/#progress-tracking