Top Menu

Jump to content
Home
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

General discussion
  1. OpenProject
  2. Forums
  3. General discussion
  4. %-Completion of WP cant be edited after Update

%-Completion of WP cant be edited after Update

Added by Maurice Kunze 12 months ago

Hello,

after installing the latest OpenProject Update we are facing the issue that we cant edit the %-done entry in workpackages. 
Does anyone have the same Problem?


Replies (1)

RE: %-Completion of WP cant be edited after Update - Added by Alexander Stock 11 months ago

Hi Maurice,

that has indeed changed with the 14.0 release. The % complete field ist not manually editable anymore. If you want to dive deeper into this topic, I recommend you these blog posts which explain the recent changes and the new mechanics behind progress reporting:

https://www.openproject.org/blog/changes-progress-work-estimates/
https://www.openproject.org/blog/openproject-14-0-release/

In short, % complete is calculated from entries in work and remaining work (or indirectly via status if you are using a status based progress approach).
Since this is a major change, your feedback on this is highly appreciated.

Best,

Alexander