Top Menu

Jump to content
Home
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

General discussion
  1. OpenProject
  2. Forums
  3. General discussion
  4. How can I see overtime for tasks

How can I see overtime for tasks

Added by Виталий ПМ over 1 year ago

Hi, I'm new to OP. 
Today I have created one task in a separate project, then set dates from 06 to 07 december, set estimated hours to 16, set spent hours to 24, set progress 100%, set hours left to 0, set status to closed.

Where can I see that overtime for all tasks is 8 hours?

/projects/p1/cost_reports - doesn not have a column called "overtime".


Replies (2)

RE: How can I see overtime for tasks - Added by Alexander Stock over 1 year ago

Hi Виталий,

maybe this user guide on the current resource planning possibilities helps you with this topic:

https://www.openproject.org/docs/use-cases/resource-management/

There is also this EPIC that describes what needs to be done to realize the process you described. Feel free to add you comment in the comment section there if you want to add something for further specification: https://community.openproject.org/wp/22800

Best

Alexander

RE: How can I see overtime for tasks - Added by Heather Hernan over 1 year ago

Alexander Stock wrote:

Hi Виталий,

maybe this user guide on the current resource planning possibilities helps you with this topic:

https://www.openproject.org/docs/use-cases/resource-management/ 

There is also this EPIC that describes what needs to be done to realize the process you described. Feel free to add you comment in the comment section there if you want to add something for further specification: https://community.openproject.org/wp/22800

Best

Alexander

Thanks! This guide is what I am looking for.