Content
You are here:
How can I see overtime for tasks
Added by Виталий ПМ 10 months ago
Hi, I'm new to OP.
Today I have created one task in a separate project, then set dates from 06 to 07 december, set estimated hours to 16, set spent hours to 24, set progress 100%, set hours left to 0, set status to closed.
Where can I see that overtime for all tasks is 8 hours?
/projects/p1/cost_reports - doesn not have a column called "overtime".
Replies (2)
Hi Виталий,
maybe this user guide on the current resource planning possibilities helps you with this topic:
https://www.openproject.org/docs/use-cases/resource-management/
There is also this EPIC that describes what needs to be done to realize the process you described. Feel free to add you comment in the comment section there if you want to add something for further specification: https://community.openproject.org/wp/22800
Best
Alexander
Alexander Stock wrote:
Thanks! This guide is what I am looking for.