Recalculate work packages start date with relations after change
Added by Antonio Cape over 1 year ago
Hi everyone.
I'm looking for a way to recalculate the start dates of tasks that follows another task when the latter is shorted.
Task1: ends on July, 31st.
Task2: follows Task1, starting on August, 1st.
Should I change the end date of Task 1 on July, 20th, Task2 start will remain on August, 1st.
This causes some troubles when the following linked tasks are more than 30, is there a way to make Open Project to "shrink" back Task2 to July, 21st?
Thank you for the attention, hope to hear soon from you.
Cheers!
Cape
Replies (4)
Hi everyone,
I do have similar issue with my projects: is there a way to automatically recalculate the starting date of a task which follows another task when the last one is shorted?
Thanks in advance.
Best,
G
Hello Antonio
this Feature Request sounds very similar to your description. It is currently part of the wish list.
I just added +2 votes for you and Giacomo. Please leave a comment there if you feel any information is missing.
Kind regards
Alexander
Hello, this feature could really help us. It is very difficult to modify the dates in the related tasks manually.
Thank you in advance.
Jan
Hi Jan
I added your vote to feature request #46139 and encourage you to add your comment if you want to add something for further specification of this request.
Best
Alexander