Top Menu

Jump to content
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    Home
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      OpenProject ID Google

Side Menu

Collapse project menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

Expand project menu
General discussion
  1. OpenProject Community
  2. OpenProject
  3. Forums
  4. General discussion
  5. Recalculate work packages start date with relations after change

Recalculate work packages start date with relations after change

Added by Antonio Cape about 2 years ago

Hi everyone.

I'm looking for a way to recalculate the start dates of tasks that follows another task when the latter is shorted.

Task1: ends on July, 31st.

Task2: follows Task1, starting on August, 1st.

Should I change the end date of Task 1 on July, 20th, Task2 start will remain on August, 1st.

This causes some troubles when the following linked tasks are more than 30, is there a way to make Open Project to "shrink" back Task2 to July, 21st?

Thank you for the attention, hope to hear soon from you.

Cheers!

Cape


Replies (4)

RE: Recalculate work packages start date with relations after change - Added by Giacomo Sacchetti about 2 years ago

Hi everyone,

I do have similar issue with my projects: is there a way to automatically recalculate the starting date of a task which follows another task when the last one is shorted?

Thanks in advance.

Best,

G

RE: Recalculate work packages start date with relations after change - Added by Alexander Stock about 2 years ago

Hello Antonio

this Feature Request sounds very similar to your description. It is currently part of the wish list.
I just added +2 votes for you and Giacomo. Please leave a comment there if you feel any information is missing.

Kind regards

Alexander

RE: Recalculate work packages start date with relations after change - Added by J. F. almost 2 years ago

Hello, this feature could really help us.  It is very difficult to modify the dates in the related tasks manually. 

Thank you in advance.

Jan

RE: Recalculate work packages start date with relations after change - Added by Alexander Stock almost 2 years ago

Hi Jan

I added your vote to feature request #46139 and encourage you to add your comment if you want to add something for further specification of this request.

Best

Alexander