Content
You are here:
Assign estimated effort per personnel cost to the work package
Added by Stephan Gottlieb over 1 year ago
Hello,
I would like to display the personnel costs per work package in the work package view from the estimated effort. The project is not started yet, so there are no hours booked yet. The hourly rates are assigned to the Mitarbeitet the time effort is also assigned to the work package together with the Mitarbeite.How can I solve the problem. Thank you in advance.
Replies (1)
Hello Stephan
the estimated effort field does not relate to the values linked to the times booked through the budget.
Therefore, there is no monetary calculation with this field. The personnel costs are only calculated with the actual booked times. These can then also be displayed in the view.
There is already a similar feature request on this topic (Feature Request). Please leave a +1 vote there to be considered for future development.