Top Menu

Jump to content
Home
    • Projects
    • Activity
    • Work packages
    • Calendars
    • Team planners
    • Boards
    • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?
      Create a new account

      or sign in with your existing account

      Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • Forums
  • Feature tour
    Feature tour
You are here:
  • Forums
  • General discussion

Content

How to let OpenProject determines end date of a task based on contributor other activity

Added by destroyedlolo Faillie 5 months ago

Hello,

I'm currently conducting a PoC in order to evaluate OpenProject as per my own team.

I can't find a way to let OpenProject determines itself end date of a task. I mean, a task has only one contributor, I specify the start date and the expected duration and I would loke OpenProject to tell which will be the end date taking in account already booked time of the contributor.

Can someone guide me how to do it ?

Thanks

Laurent


Replies (3)

RE: How to let OpenProject determines end date of a task based on contributor other activity - Added by Samantha Machon 5 months ago

Hello Laurent, 

I am afraid that it is not possible to calculate the end date of a work package based on a start date and logged time. 

However, there is a similar feature request about calculating the end date based on the start date and estimated time: https://community.openproject.org/projects/openproject/work_packages/23318/activity

You do also have the possibility to create a feature request as described here: https://www.openproject.org/docs/development/submit-feature-idea/

Best regards
Samantha

RE: How to let OpenProject determines end date of a task based on contributor other activity - Added by destroyedlolo Faillie 5 months ago

Hi Samantha,

Thanks for your reply : voted on this feature request as it's really a must-have for such tool.

Best regards,

Laurent

RE: How to let OpenProject determines end date of a task based on contributor other activity - Added by Samantha Machon 5 months ago

Hi Laurent, 

We have added your vote to the feature request. 

Best regards
Samantha