Content
You are here:
Work packages
Added by Michal Rada almost 2 years ago
Hi,
I'm creating a template for a project. When I would like to see more projects than one then I don't know which phase is for which project. I tried to find a way how to create a template with activities that contain the Project name as part of the view or Subject attribute. I can add a column Project in the activity overview but it's not possible to add to the Gantt chart or Calendar.
Does exist any option which could add the attribute Project Name to Activity Subject or somehow create a Custom field which could be defined as Activity Subject and Project name?
I'm using "OpenProject 12.4.1"
Thank you a lot for any help
Michal
Replies (1)
Hi,
I found the view which will be perfect. The view for team planner contains the project name in the callendar. How to use Project name as part of Gantt chart view? There are these parameters Status, ID - project name and subject.
https://www.openproject.org/docs/user-guide/team-planner/TeamPlanner-12.4-removeAssigneeDates-579205c6.png
In the Gantt chart I can add only 3 parameters. Start and Finish date and Subject but if I need combine more projects then it's not enough.
thank you
Michal