Top Menu

Jump to content
Home
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

General discussion
  1. OpenProject
  2. Forums
  3. General discussion
  4. % Progress with child tasks

% Progress with child tasks

Added by Mr Emery over 2 years ago

Hey everyone, 

I have just gotten set up with OpenProject but I am stuck with the progress% option. I am putting together a training tracker using tasks/child tasks for the modules and I have set up statutes to change the % complete for the tasks but I am having some trouble getting this to reflect on the parent task as shown below - Is there another way I should approach this?

Many thanks in advance everyone :)


Replies (1)

RE: % Progress with child tasks - Added by Samantha Machon over 2 years ago

Hi Declan, 

With the status based progress tracking, there is no roll-up of progress in the work package table hierarchy as the progress is based on the status and it’s associated progress value.

You can track the progress manually instead as described here: https://www.openproject.org/docs/user-guide/time-and-costs/progress-tracking/#manual-progress-tracking

Best regards
Samantha