Time shift of the entire project
Added by Jonas Meyer about 3 years ago
Hello,
Is there a possibility to shift the entire project in terms of time? For example: My project gets postponed for one month and I therefore need to apply this shift to the entire project before it starts. Can I do this change without applying this step manually?
Thank you for your advice :)
Kind regards,
Jonas
Replies (1)
Hi Jonas,
You can edit it within one action only if you have configured your project with a critical path method.