Top Menu

Jump to content
Home
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

General discussion
  1. OpenProject
  2. Forums
  3. General discussion
  4. Custom fields configuration

Custom fields configuration

Added by Cedric TOMASETIG about 3 years ago

Hey there,

I warn you, I am an OpenProject beginner! Now that you know it, here is my request:

I would like to create a custom field where I can manually indicate progress for each phase I have. Currently, if you have 4 phases, one of which is 25% progress, I'd like to customize that and think it might be possible to do that with a custom field?

For example :
Phase 1 represents 20%
Stage 2 - 40%
Stage3 - 30%
Stage 4 - 10%

Of course, for each task or milestone achieved, the percentage will automatically update accordingly.

If you have any proposition, be my guest ! :)


Replies (2)

RE: Custom fields configuration - Added by Samantha Machon about 3 years ago

Hi Cedric, 

We have a feature request regarding calculating the progress % based on WP-progress of child-WP: https://community.openproject.org/projects/openproject/work_packages/31306/activity
This seems to be very similar to your question. Let me know if it fits and I can add a vote for you. 

Have a great weekend,
Samantha

RE: Custom fields configuration - Added by Cedric TOMASETIG about 3 years ago

Hi Samantha,

The feature I'm looking for is the possibility to configure the percentage that each phase of the project represent and, in the same tame, that this percentage automaticaly increase when WP-child are completed.

For now, I do it with a basic calculation in Excel : 

Phase 1 - 50% of progress in OpenProject, this phase represents 30% of my project so the calculation is the following one : 50%*0,3.

Same for the other phases.

Not sure that this feature request is about the same thing.

Have a great week !

Cedric