Top Menu

Jump to content
Home
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

General discussion
  1. OpenProject
  2. Forums
  3. General discussion
  4. work load and deadlines

work load and deadlines

Added by Thomas CHALMEL over 4 years ago

Hi,

How to set "work load" ("charge" in french)  and "deadlines"  ("délais" in french) on a task ? (I'dont find how to do this...

I'm planning a new projetc, and need to creat some task.

A Teams for a task engaged to deliver this task on a specifique duration (5 days) for a specific workload (cost 1.5 days)

On Openproject i'v found how to set the workload cost but not the duration ...

My project is not yet run, i'm planing it, so i have not yet real date for my diferents task.

How to set this information ?


Replies (1)

RE: work load and deadlines - Added by Max Mutzge over 4 years ago

Hi Thomas,

for the work load you could use the attribute "Estimated time" and for the duration you could add a custom field "Duration" (https://docs.openproject.org/system-admin-guide/custom-fields/). I'm sorry I don't know the French words for this. 
You could also show the duration by simply setting a start date and finish date for the task.

Kind regards
Matthias