Top Menu

Jump to content
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    Home
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      OpenProject ID Google

Side Menu

Collapse project menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

Expand project menu
General discussion
  1. OpenProject Community
  2. OpenProject
  3. Forums
  4. General discussion
  5. work load and deadlines

work load and deadlines

Added by Thomas CHALMEL over 4 years ago

Hi,

How to set "work load" ("charge" in french)  and "deadlines"  ("délais" in french) on a task ? (I'dont find how to do this...

I'm planning a new projetc, and need to creat some task.

A Teams for a task engaged to deliver this task on a specifique duration (5 days) for a specific workload (cost 1.5 days)

On Openproject i'v found how to set the workload cost but not the duration ...

My project is not yet run, i'm planing it, so i have not yet real date for my diferents task.

How to set this information ?


Replies (1)

RE: work load and deadlines - Added by Max Mutzge over 4 years ago

Hi Thomas,

for the work load you could use the attribute "Estimated time" and for the duration you could add a custom field "Duration" (https://docs.openproject.org/system-admin-guide/custom-fields/). I'm sorry I don't know the French words for this. 
You could also show the duration by simply setting a start date and finish date for the task.

Kind regards
Matthias