Top Menu

Jump to content
Home
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

General discussion
  1. OpenProject
  2. Forums
  3. General discussion
  4. how to import project plan in excel?

how to import project plan in excel?

Added by sunny sun almost 6 years ago

can we import project plan in excel format?

can we breakdown task into sub-task?

can we set only allow specified person to modify milestone?


Replies (4)

RE: how to import project plan in excel? - Added by Robin Wagner almost 6 years ago

Hello Sunny,

yes, you can import a project plan from Excel to OpenProject. There is a separate Excel synchronization template available for this. 

You can find download the template and find futher information here: https://www.openproject.org/synchronize-excel-openproject/.

You can also break tasks / work packages into subtasks. An easy way to do this is by right-clicking on a task and and selecting "Create new child".

The roles in OpenProject provide permissions to create or edit work packages (this provides permissions for all work packages in the project - it is not possible to only provide permissions to only certain work package types (such as milestones)). You can e.g. add users with the role "Reader" to a project in order to allow them to only see tasks but not to modify them.

RE: RE: how to import project plan in excel? - Added by sunny sun almost 6 years ago

Hi,Robin

Thanks for your quick answer. Is there any way for us to set one project plan as project baseline, and if any one want to change it, need to go through change process to get approval?

RE: RE: RE: how to import project plan in excel? - Added by sunny sun almost 6 years ago

Still want an answer for the following questions:

  1. from where to see the task that has closed?
  2. from where to get the document that has uploaded int the task?
  3. how to use the item of "category"? only for the filter using?
  4. what is the difference for assignee and accountable?
  5. how to manage the document ,the better way is to use wiki?

RE: how to import project plan in excel? - Added by Robin Wagner almost 6 years ago

Hi Sunny,

we are evaluating a planning comparison which would show you the differences make to a project schedule. You would define a baseline or specify a timeframe you want to compare to the current schedule and see the differences. There exists already a feature request for this: #26448. Feel free to comment on this.

Regarding your other questions:

1. from where to see the task that has closed?

On the work package page, expand the filter section and filter for "Status: closed". This will show you all completed work packages.

2. from where to get the document that has uploaded int the task?

The documents uploaded to a task are shown in the "Files" section directly on the "Overview" tab. Simply open a work package and scroll down. Just above the "Last activity" section you will see the uploaded files.

3. how to use the item of "category"? only for the filter using?

You can use the "Category" to categorize work packages and also to automatically assign a user to a work package when you create a new task and select the category (without setting an Assignee). If you specified an assignee in the category creation, that assignee will be set automatically. You can filter based on the category, but you can also group by it and add it as a column to the work package page.

4. what is the difference for assignee and accountable?

The assignee is the person (or group) who is working on a work package, while the accountable is the person responsible for the completion. An accountable could be e.g. the project manager, while the assignee can be e.g. a project member currently working on a task. Typically, the accountable does not change, while the assignee changes quite often - depending on who is currently working on the task.

5. how to manage the document ,the better way is to use wiki?

Apart from directly uploading documents to work packages, you can use the separate "Documents" module. You can activate this within a project by navigating to "Project settings", selecting the "Modules" tab and checking "Documents". If you work with wiki pages and would like to add images, it makes sense to upload these directly to the wiki page.