Top Menu

Jump to content
Home
    Modules
      • Projects
      • Activity
      • Work packages
      • Gantt charts
      • Calendars
      • Team planners
      • Boards
      • News
    • Getting started
    • Introduction video
      Welcome to OpenProject Community
      Get a quick overview of project management and team collaboration with OpenProject. You can restart this video from the help menu.

    • Help and support
    • Upgrade to Enterprise edition
    • User guides
    • Videos
    • Shortcuts
    • Community forum
    • Enterprise support

    • Additional resources
    • Data privacy and security policy
    • Digital accessibility (DE)
    • OpenProject website
    • Security alerts / Newsletter
    • OpenProject blog
    • Release notes
    • Report a bug
    • Development roadmap
    • Add and edit translations
    • API documentation
  • Sign in
      Forgot your password?

      or sign in with your existing account

      Google

Side Menu

  • Overview
  • Activity
    Activity
  • Roadmap
  • Work packages
    Work packages
  • Gantt charts
    Gantt charts
  • Calendars
    Calendars
  • Team planners
    Team planners
  • Boards
    Boards
  • News
  • Forums

Content

General discussion
  1. OpenProject
  2. Forums
  3. General discussion
  4. Show baselines versus actuals in gantt chart

Show baselines versus actuals in gantt chart

Added by Zehra Mehdi about 6 years ago

I am looking for a feature that is similar to one in MS Project. The ability to see in Gantt charts - both the baseline start and finish and actual start and finish. Is there a way to accomplish this in OpenProject?


Replies (3)

RE: Show baselines versus actuals in gantt chart - Added by Zack Glennie about 6 years ago

I have not used MS Project before. 

What is a "baseline" start/finish, vs an "actual" start/finish? 

Is there a moment near the end of the planning stage (for a given scope of work), where the start/end dates for that scope of work become "official", and are treated as baselines?

RE: Show baselines versus actuals in gantt chart - Added by Zehra Mehdi about 6 years ago

Yes, you got it! Say for instance, we estimated a certain task to start on a specific day and finish in 10 days, but in reality to started 2 days late, and took 12 days instead. I am looking at options to compare the actuals to the baselines to determine how far we drifted off and dig into possible causes - this would help in future planning.

RE: Show baselines versus actuals in gantt chart - Added by Zack Glennie about 6 years ago

Yup, I can see how such a thing might be useful in certain situations, particularly if there is a well-defined "kickoff" ceremony, where the plan becomes "anchored" to start on a specific day and finish on a specific day. 

When you initially create a task in OP and give it a start and end date, they are very flexible, you can update them just by dragging handles on the Gantt chart, so at some point you would have to say "I'm done writing the plan, we're now moving into executing the plan" -- this would be perhaps the kickoff ceremony.

I haven't seen anything in OP that represents this "kickoff" or "anchoring" event, so I don't think that the feature you are describing is possible (unless such a "kickoff" event feature is added).

But I could be wrong...I'm new here, and I'm not using all of the modules for my org.