Is it possible to synchronize the percentage of done with state?

Is it possible to assign a percentage of done to a specific workpackage state?

Message actions

Hi Sebastian,

yes you can:

Administration -> System settings -> Work package tracking -> Calculate the work package done ratio with -> Use the work package status.

Here you can change the percentage done for each status:

Administration -> Work package status -> “Status” -> Progress %.