Workdays/Vacation

Hello,

is there a way to define constraints (such as Holidays per user/group, in case of an international team)?
without showing it in the timeline.

Thanks
Assaf

Message actions

Hi Assaf,

this is unfortunately not possible yet.
There is a feature request for this. Feel free to add a comment if you miss anything: OP-1803.

Best,
Robin

Message actions

Is there ANY way to specify weekends/holidays and for openproject to avoid them?

Message actions

This feature has been implemented.