I dont see subproject tasks in the timeline view of my parent project

Hi everyone, the problem is as stated in the topic, unfortunately I cannot see tasks of subprojects associated with my project on the timeline site of my project.

Even if I choose to include subprojects in the edit timeline report project timeline window, these tasks do not appear on the timeline, can someone offer help?

Thanks & Best Regards

Message actions

Have you enabled status reporting in subproject?
https://www.openproject.org/help/user-guides/project-settings/manage-status-reporting/

Regards,
Igor

Message actions

ah okay i didnt do that, thanks!