Hi all,
I'm actually working on project budgets, labor costs and time tracking.
I configured for my working package a budget of 100h (planned labor costs). If I track my time via "my timetracking" I cannot see in the budget list the correct labor costs...little bit confusing.
Working Package shows the tracked time of 4,25h
Budget shows the time of 2h
Can anybody help?
Thanks & Regards
Melanie
Replies (1)
Hi Melanie,
I presume you did everything right, but there's a bug you stumbled upon. If you book times on a work package twice, without adding time to any other work package associated with this budget in the meantime, the IST list is not complete, even though the sum is correct. This bug report aims to deal with this problem:
Best
Alexander