How to create Start-to-Start connection between tasks?

Dear developers,
how to create "Start-To-Start" connection between tasks?
The connection type needed if two or more tasks should start simultaneously.
---
With best regards,
Yuriy Arseniev

Message actions

Hello Yuriy,

a "start-to-start" relationship is currently not yet possible in OpenProject.

Depending on your situation, the use of a common preceding task and the use of "finish to start" relationship may work as a workaround:

This way, the two following tasks can be worked on as soon as the preceding task has been completed.