Hi everyone 

For us, the only obstacle to the adoption of openproject is the impossibility of changing the order of the tasks. 

We tried to add a custom field and use it as a sort, but we lose the hierarchical view of the tasks. 

The use of the gant partly solves the problem but we use it only in structured projects. Most projects are a very simple todo list. 

For us it is essential to be able to reorder the tasks, for example: 
At the beginning of the project we insert task 1, task 2 and task 3. But after a few weeks a new task is needed and must be done after 2 but before 3. We can insert dependencies but we do not want to set up the gant, we need of a simple and reorderable list. 

it's really important for us to find a solution, 
Thank you

Message actions

Its possible to reorder stories using the Backlogs plugins.

Message actions

Hi Ricardo 
Thanks for the help, but unfortunately (if I understand correctly) the backlogs do not maintain the hierarchical view. It's correct? 

Thanks again

Message actions

Hi Ricardo 
Thanks for the help, but unfortunately (if I understand correctly) the backlogs do not maintain the hierarchical view. It's correct? 

Thanks again

Message actions

They don't. And tasks aren't displayed there, only stories.

Message actions

Thanks, so it's not the solution I was looking for, are there any other alternatives?