Content
Activity
From 01/31/2025 to 02/06/2025
02/06/2025
-
updated by
Jens Ulferts on 02/06/2025 11:21 AM - Assignee set to Markus Kahl
-
updated by
Oliver Günther on 02/06/2025 11:11 AM - Type changed from Deliverable to Implementation
- Finish date changed from 01/15/2025 to 02/28/2025
- Status changed from in progress to needs review
- Assignee deleted (
Oliver Günther) - Version set to 15.3.0
- Start date set to 02/06/2025
- Duration set to 17 days
- Requires doc change set to No
-
updated by
GitHub on 02/06/2025 11:11 AM - Comment added
-
updated by
GitHub on 02/06/2025 11:11 AM - Comment added
-
updated by
Oliver Günther on 02/06/2025 10:32 AM - Status changed from new to in progress
Also available in: Atom