* Project overview
* There is a box table in the project overview that contains a table that lists all phases and gates which are active in the project. This replaces the dates in the sidebar.
* In the show mode there is an edit button above the table.
* In the edit mode there is save button below the table.
* Automatic scheduling
* Changing the finish date of a phase triggers the rescheduling of succeeding phases/gates. Those automatic changes are only saved after explicit saving the form.
* In case finish dates of phases are empty they are not set by changing the dates of predecessors. Dates can be deleted from phases and gates.
* Active phases/gates are sequential. The sequence is defined by the order of the phases/gates in the administration.
* In case a phase/gate is inactive in a project, the next active phase/gate is considered to be the successor. Multiple inactive phases/gates can be ignored that way.
* Phases/gates not active in the project are not scheduled. In case a phase/gate is inactivated, it keeps its dates.
* Activating and deactivating a stage or gate does not trigger a rescheduling.
* Only working days can be selected. Non-working days are excluding from rescheduling. Finish days can not be non-working days.
* Activity
* The activity page includes the changes to phases and gates
* Work package
* A work package can be optionally assigned to a phase (single-select).
* The work package type form configuration also includes the attributes (phase/gate).
* The assignment of work packages to phases does not impact scheduling.
* Work packages can be filtered for their phases.
* Permissions
* There is a separate project permission to activate and deactivate project phases and gates.
* There is a separate project permission to edit phases and gates.
* There is a box
* In the show mode there is an edit button above the table.
* In the edit mode there is save button below the table.
* Automatic scheduling
* Changing the finish date of a phase triggers the rescheduling of succeeding phases/gates. Those automatic changes are only saved after explicit saving the form.
* In case finish dates of phases are empty they are not set by changing the dates of predecessors. Dates can be deleted from phases and gates.
* Active phases/gates are sequential. The sequence is defined by the order of the phases/gates in the administration.
* In case a phase/gate is inactive in a project, the next active phase/gate is considered to be the successor. Multiple inactive phases/gates can be ignored that way.
* Phases/gates not active in the project are not scheduled. In case a phase/gate is inactivated, it keeps its dates.
* Activating and deactivating a stage or gate does not trigger a rescheduling.
* Only working days can be selected. Non-working days are excluding from rescheduling. Finish days can not be non-working days.
* Activity
* The activity page includes the changes to phases and gates
* Work package
* A work package can be optionally assigned to a phase (single-select).
* The work package type form configuration also includes the attributes (phase/gate).
* The assignment of work packages to phases does not impact scheduling.
* Work packages can be filtered for their phases.
* Permissions
* There is a separate project permission to activate and deactivate project phases and gates.
* There is a separate project permission to edit phases and gates.