**As** a project portfolio manager
**I want to** have stages and gates adjust automatically based on changes to preceding/succeeding stages and gates
**so that** administration is simpler and less error prone.
**Acceptance criteria**
* \[open\] Are gaps allowed?
* \[open\] When decreasing a date, will the successor's dates be decreased as well?
* \[open\] Do we want to show all the changes in the modal before the user commits?
* \[open\] Do we want to introduce modification by durations?
* If so, can a duration be set independently (without start and end date set)?
* \[open\] Empty successors
**I want to** have stages and gates adjust automatically based on changes to preceding/succeeding stages and gates
**so that** administration is simpler and less error prone.
**Acceptance criteria**
* \[open\] Are gaps allowed?
* \[open\] When decreasing a date, will the successor's dates be decreased as well?
* \[open\] Do we want to show all the changes in the modal before the user commits?
* \[open\] Do we want to introduce modification by durations?
* If so, can a duration be set independently (without start and end date set)?
* \[open\] Empty successors