Updated by Wieland Lindenthal over 3 years ago
### <img class="op-uc-image op-uc-image_inline" src="/api/v3/attachments/51657/content">
### Steps to reproduce
* Create a work package called "Parent"
* Create a I cannot say yet for sure
I observed it here on #41400, comment #20. Andreas only worked on child work package called "Child"
* Add start and finish date to "Child" packages. So the parent got somewhat affected by the automatic scheduling.
### What is the buggy behavior?
* In this example the Andreas did add or edit a child work package, not setting any dates.
* The change in dates on scheduler created comment #20 but did not put the parent are shown in message. This made me believe/doubt that Andreas did the activity as done by the user but it actually was updated automatically. A comment telling it was rescheduled automatically is missing. scheduling directly himself (which he didn't)
### What is the expected behavior?
1. Whenever related work packages change their date values due to automatic scheduling it leaves a clear message. message
### Environment information
_Please check and fill out the following details to help us identify in what versions and distributions of OpenProject the error occurs_
**OpenProject installation type**
Here on community and on QA community.
### Steps to reproduce
* Create a work package called "Parent"
* Create a
I observed it here on #41400, comment #20. Andreas only worked on
* Add start and finish date to "Child"
### What is the buggy behavior?
*
*
### What is the expected behavior?
1. Whenever related work packages change their date values due to automatic scheduling it leaves a clear message.
### Environment information
Here on community and on QA