Updated by Attila Dombi almost 4 years ago
Copied from <mention class="mention" data-id="31992" data-type="work_package" data-text="#31992">#31992</mention> (which is still authoritative so double check the requirements there):
> * If dates are changed (which affects duration), then that will considered a date changed.
> * Ideally, the duration is also specified in brackets. Eg. "Finish date changed to 2022.10.13 (duration is now 3 days)".
> * This is the same if duration is changed (and this affects finish date), then the display will be the same.
> * For work packages with only duration, then the duration will be an additional activity that is displayed, if the duration is altered.
> * eg. "Duration changed to 3 days".
If this is implemented in 12.2, it needs to be hidden behind a feature flag.
> * Ideally, the duration is also specified in brackets. Eg. "Finish date changed to 2022.10.13 (duration is now 3 days)".
> * This is the same if duration is changed (and this affects finish date), then the display will be the same.
> * For work packages with only duration, then the duration will be an additional activity that is displayed, if the duration is altered.
> * eg. "Duration changed to 3 days".
If this is implemented in 12.2, it needs to be hidden behind a feature flag.