# Situation
As mentioned in [Bug: Work Package Done... (#36160) | OpenProject | OpenProject Community](https://community.openproject.org/projects/openproject/work_packages/36160/activity) as a bug, we would like to suggest as a feature for the future.
Would be very helpful.
# User Story
As I user
I want to automatically let OP determine the progress% of a work-package by its children statuses
so that I do not have to do the same work redundantly by setting both.
**Acceptance Criteria**
* third option in settings "auto-progress"
* progress of a leaf task is determined by status
* progress of a non-leaf task is determined by the progress of its children helpfull.
As mentioned in [Bug: Work Package Done... (#36160) | OpenProject | OpenProject Community](https://community.openproject.org/projects/openproject/work_packages/36160/activity) as a bug, we would like to suggest as a feature for the future.
# User Story
As I user
I want to automatically let OP determine the progress% of a work-package by its children statuses
so that I do not have to do the same work redundantly by setting both.
**Acceptance Criteria**
* third option in settings "auto-progress"
* progress of a leaf task is determined by status
* progress of a non-leaf task is determined by the progress of its children