**Precondition**
- Work package priority exists.
- Work package module is activated.
**Steps to reproduce**
1. Go to Modules \> Administration \> Enumerations.
2. Click on work package priority, uncheck “Active” and click Save.
3. Go to Work packages \> New work packages in side navigation.
4. (The deactivated work package priority can still be selected.)
**Actual behavior**
- Deactivating a work package priority has no effect.
**Expected behavior**
- It should not be possible to assign deactivated work package priorities to work packages.
- Deactivated It should not be possible to deactivate work package priorities of existing work packages that are kept (but cannot be selected again once the assigned to work package priority is changed to a different value). packages.
- Work package priority exists.
- Work package module is activated.
**Steps to reproduce**
1. Go to Modules \> Administration \> Enumerations.
2. Click on work package priority, uncheck “Active” and click Save.
3. Go to Work packages \> New work packages in side navigation.
4. (The deactivated work package priority can still be selected.)
**Actual behavior**
- Deactivating a work package priority has no effect.
**Expected behavior**
- It should not be possible to assign deactivated work package priorities to work packages.
- Deactivated