Updated by Max Mutzge over 5 years ago
**As** a project manager
**I want to** control the progress bar calculation by excluding Work packages (by type Typ or status) Status)
**so that** the progress value can be use for EVA reports. Each additional work package will change the progress bar, even that work package is just a little task or a reminder for a person.
Instead of moving those task into a separate phase or topic, the task should be marked as "exclude from progress" or similiar. similiar.
**Acceptance criteria**
* option to exclude a work package from progress calculation
* done by a status or an boolean option at the work package
**I want to** control the progress bar calculation by excluding Work packages (by type
**so that** the progress value can be use for EVA reports. Each additional work package will change the progress bar, even that work package is just a little task or a reminder for a person.
Instead of moving those task into a separate phase or topic, the task should be marked as "exclude from progress" or similiar.
**Acceptance criteria**
* option to exclude a work package from progress calculation
* done by a status or an boolean option at the work package