# Problem
* It is currently hard to create project schedules as when work packages span a weekend. In these cases the weekend days are counted as normal working days.
* When projects change the start day of a work package the calculation of the finish date does not take into account any non-working days between the start and the finish date.
> **Example:** A task starts on Monday and finishs on Friday. If the task is delayed by one day the finish date is set for the Saturday. Since Saturday is a non-working day in this scenario the more accurate calculation for the finish date would be Monday.
# Solution
* For each each installation an Admin can set a default working-day calendar which is preset for all projects.
* The calculation of the finish date takes the availability calendar into account (see example in the problem statement).
## Visuals
<figure class="image op-uc-figure" style="width:72.77%;"><div op-uc-figure"><div class="op-uc-figure--content"><img class="op-uc-image" src="/api/v3/attachments/20674/content"></div></figure>
# **Out of Scope for the MVC**
* Adding public holidays to the seed data.
* Selecting non-working days on a project level.
* Non-working-days of individual team members.
* Subscribe to external calendars, e.g. Google calendars.
* Duration calculation based on people assignments and work (effort) estimate (fixed work mode).
* It is currently hard to create project schedules as when work packages span a weekend. In these cases the weekend days are counted as normal working days.
* When projects change the start day of a work package the calculation of the finish date does not take into account any non-working days between the start and the finish date.
> **Example:** A task starts on Monday and finishs on Friday. If the task is delayed by one day the finish date is set for the Saturday. Since Saturday is a non-working day in this scenario the more accurate calculation for the finish date would be Monday.
# Solution
* For each each installation an Admin can set a default working-day calendar which is preset for all projects.
* The calculation of the finish date takes the availability calendar into account (see example in the problem statement).
## Visuals
<figure class="image op-uc-figure" style="width:72.77%;"><div
# **Out of Scope for the MVC**
* Adding public holidays to the seed data.
* Selecting non-working days on a project level.
* Non-working-days of individual team members.
* Subscribe to external calendars, e.g. Google calendars.
* Duration calculation based on people assignments and work (effort) estimate (fixed work mode).