**As** a project manager
**I want** to easily and quickly schedule parent work packages directly from the Gantt chart
**so that** I don't have to open the date picker to plan parent work packages.
Current behavior (scheduling parent work packages only possible through date picker):
<figure class="image"><img src="/api/v3/attachments/19093/content" alt=""></figure>
**Acceptance criteria**
* When activating the Add entry to context menu to switch between manual and automatic scheduling mode for a parent - directly from work package, it should be possible to schedule that parent work package directly from the / Gantt chart.
* Possibly related: Switching between manual and automatic scheduling mode (#34705)
**Technical notes:**
<figure class="image"><img src="/api/v3/attachments/19223/content"></figure>
**I want** to easily and quickly schedule parent work packages directly from the Gantt chart
**so that** I don't have to open the date picker to plan parent work packages.
Current behavior (scheduling parent work packages only possible through date picker):
<figure class="image"><img src="/api/v3/attachments/19093/content" alt=""></figure>
**Acceptance criteria**
* When activating the
* Possibly related: Switching between manual and automatic scheduling mode (#34705)
**Technical notes:**
<figure class="image"><img src="/api/v3/attachments/19223/content"></figure>