Updated by Niels Lindenthal almost 6 years ago
**Scenario:**
1. Create a work package "Parent 1".
2. Add a start-date and a finish-date.
3. Switch to automatic scheduling mode.
4. Add a work child element without dates.
**Current behavior:**
* By adding a child work package the dates of the parent worpackage get lost.
* The dates in the create form of the child work package is empty.
**Expected behavior:**
* In the create form of the sub work package the parent's dates are pre-selected.
* When adding a new child work package the default value is derived from the parent's work package.
**Open:**
* The problem mainly occurs when adding the first children work package. So we need to discuss whether we want to have specific behavior only for the first value.
1. Create a work package "Parent 1".
2. Add a start-date and a finish-date.
3. Switch to automatic scheduling mode.
4. Add a work child element without dates.
**Current behavior:**
* By adding a child work package the dates of the parent worpackage get lost.
* The dates in the create form of the child work package is empty.
**Expected behavior:**
* In the create form of the sub work package the parent's dates are pre-selected.
* When adding a new child work package the default value is derived from the parent's work package.
**Open:**
* The problem mainly occurs when adding the first children work package. So we need to discuss whether we want to have specific behavior only for the first value.