Content
View differences
Updated by Oliver Günther almost 8 years ago
**Preconditions**
- Work package module activated.
- Parent work package exists in project A.
- Child work package(s) exist in project B.
- Time logged on work package in project B (inherited to project A) - with date that is significantly in the past (e.g. 4 month prior).
**Steps to reproduce**
1. Copy project A (with work packages).
2. Rename copied project A.
3. Create a parent-child relationship from work package with logged time in project B to copied project A.
4. Go to copied project A, open copied work package (which has logged time inherited from WP in project B).
5. Click on logged time link.
**Actual behavior**
- Time entries inherited from sub work packages not shown.
- This happens both with and without activated cost report module.
**Expected behavior**
- Time entries inherited from sub work packages shown.
**Gif**

**Example**
https://demoproject.openproject.com/projects/demo-project/work\_packages/476/activity
**QA system**
- OpenProject 7.3
- Work package module activated.
- Parent work package exists in project A.
- Child work package(s) exist in project B.
- Time logged on work package in project B (inherited to project A) - with date that is significantly in the past (e.g. 4 month prior).
**Steps to reproduce**
1. Copy project A (with work packages).
2. Rename copied project A.
3. Create a parent-child relationship from work package with logged time in project B to copied project A.
4. Go to copied project A, open copied work package (which has logged time inherited from WP in project B).
5. Click on logged time link.
**Actual behavior**
- Time entries inherited from sub work packages not shown.
- This happens both with and without activated cost report module.
**Expected behavior**
- Time entries inherited from sub work packages shown.
**Gif**

**Example**
https://demoproject.openproject.com/projects/demo-project/work\_packages/476/activity
**QA system**
- OpenProject 7.3